LATEST..          Strictly limited - exclusive full line Brake Van ride tickets available now - see Diesel Gala page for details         The Oldbury Carriage featured in the CH4 Great Rail Restoration Programme is now on Show in our C&W Workshop at Havenstreet - see blog for further details and catchup link          All operating days and events can be found on our YOUR VISIT - Timetables page          BOOKINGS for our SANTA and BOXING Day events 2018 and NEW YEAR'S DAY 2019 are already being taken. Please note that these events now have to be pre-booked and seating is allocated          Details relating to the Diesel Gala are now available on the Diesel Gala Page
LATEST UPDATES
  • TP_Mar_18_Header

BOOK YOUR TICKET

•service update•

SUN 23 SEP

we are open

WE ARE OPERATING FROM OUR
BLUE TIMETABLE

Track Pack - March 2018

April Working Weekend - Saturday 7th & Sunday 8th

Despite the Easter Weekend almost being in April, the Working Weekend will be the traditional  first full weekend in April. It seems the best option given the jobs to be carried out and will also  hopefully be more convenient for those who have other plans for that weekend.

Saturday will be spent as usual carrying out the fishplate greasing at Havenstreet, Smallbrook and Wootton stations. There will be a train service operating both days so access shouldn’t be a problem.

Sunday will either spent changing sleepers in a convenient location if numbers allow, or otherwise making a start on the lineside cutting at Havenstreet or Wootton.

Looking forward to seeing everyone at the Weekend, 8.30am at the P.Way Hut being the favoured time both days.

What's Been Going On?

The sudden arrival of a snow storm on the Thursday before the March Working Weekend had rather undesirable effects on the Weekend’s activities.  After a few phone calls on Friday afternoon it seemed sensible, given the forecast, to suggest to the mainland gang members  not to travel, and then see how many Island residents felt able to make it on the Saturday.

As was totally understandable, only a couple made it in on the Saturday morning, joined by the member from Wootton on foot in the afternoon. The day was spent continuing to fix down the chairs to the timbers on No.6 points, in the afternoon the new switches were lifted and packed with the BLH machine.
TP_Mar_18_1
The Havenstreet East End (No.6 points) work site on Monday 19th February.
The conditions eased slightly overnight and a few gang members were able to make it to Havenstreet on Sunday morning. With a lot of snow still on the track and rails it  seemed a better use of time to postpone the fishplate work and continue with the point job.

A start was made by slightly slewing the Up loop at the station end to give a better run into the new crossing. After a break for refreshments, the curved rail opposite the crossing could now be fixed down while the rest of the gang respaced the sleepers at the new joint positions on the approach track adjacent to the Bracket signal.

After a longish dinner break the final piece of rail to complete the curved part of the point was measured (three times), cut and put into place ready to be plated up before fixing down.

A big thank you to everyone who turned out in less than ideal conditions, to find themselves doing something they hadn’t expected.

What Else Has Been Going On?

With the new Operating Season on the horizon, the major priority has been to complete the works associated with No.6 points. A couple of Line Patrols at the start of March revealed nothing in need of imminent attention, so all efforts could be concentrated on the point job.

Besides a few bits of ballast tidying, the point and associated equipment were in a satisfactory condition by Friday the 16th of March and the possessions could be removed. This week was also used to carry out the necessary round of tests etc. on the rest of the S&T installation.
TP_Mar_18_2
The first movement over the new crossing took place on Tuesday 6th March.  Whilst undergoing an annual steam test, W24 was borrowed to carry out a trial run over the completed track work.
Sunday 18th March was the first day of the 2018 operating season, snow fell down on us once again! After a dicey drive to Havenstreet, the day was spent clearing snow from flangeways and pointwork to allow a (delayed and reduced) initial train service to operate.
 
The Friday Gang have disinterred their collection of machines and made a start on the lineside at Ashey Grounds. Prior to that, their main occupation had been the continued disposal of material from January’s tree works.

That’s the lot for now,
All the best,
Ian, Phil and Pete.

Join The Team

The Civil Engineering Department is responsible for all of the railway's  track, signalling equipment and lineside fencing - It's all healthy outdoor work!

Monthly working parties are organised to tackle important tasks requiring a large team, regular weekly gangs tackle lineside clearance, fencing renewals and many other maintenance tasks.  We also have our 'Friday Gang' who do a great job of keeping the lineside neat and tidy, it's Men In Sheds - but without the shed!

If you are interested in joining our team please contact the railway's Volunteer Coordinator for more details.






FOLLOW IW STEAM RAILWAY

#

NEXT EVENT

DIESEL GALA

A rare opportunity to see Diesels at work on ...

28 September - 30 September 2018

• MORE INFO • BOOK NOW

Subscribe to our mailing list

LATEST NEWS

Surprise Award for Flowery Calbourne

Surprise Award for Flowery Calbourne

• READ MORE •

BRAKE VAN RIDES EXCLUSIVE!

For the first time ever, brake van rides are being offered at this year's Diesel Gala in September. A full 10 mile...

• READ MORE •
- ARCHIVES -